At the northern facility there construction work lasts
“BELTRUBOPROVODSTROY” JSC continues work at the northern facility of SevKomNefteGas LTD at Yamalo-Nenets Autonomous District.
By the Customers order within the project “Severo-Komsomolsk interfield oil and gas pipeline construction” that lasts since December of 2020 we proceed construction of two pipelines routs.
After the successful implementation of 3 underwater crossings under the Pur River and 1 closed crossing under the communications from january to may 2021, for now our construction teams are ready to proceed with laying of the main linear part of the pipelines.
There our collegues have huge plans at the site! In the next few weeks, the “BELTRUBOPROVODSTROY” teams must weld and lay more than 30 kilometres of the pipe. To complete this task the welding work will be carried by several columns of our best welders during 24/7 despite of the short daylight period and low temperature conditions.
Glad to share the recent photos from the Purpe facility to show the construction process in the conditions of the Far North: