At our northern site the main stage of crossing construction works has been finished
At the site of Interfield oil and gas pipeline of the Severo-Komsomolskoye field Beltruboprovodstroy team has completed the construction of the final third crossing this weekend.
The works were completed due to sheduled time. As a result, in less than 4 months, we managed to complete main stage of pipelaying and implemented 3 crossings according to the approved plan: 2 oil pipeline crossings and 1 gas pipeline crossing. All the crossings of oil and gas pipelines have been performed by Beltruboprovodstroy staff by directional drilling using own equipment and utilities.
In the few next days, our team urgently needs to complete parcing of the installations and re-mobilize construction equipment to the pipe welding base in Purpe.
After the weather in the Yamal-Nenets Autonomous District become favorable for underground work, our employees will return to the site for further pipeline construction.
*the photos are for illustrative purposes only