Without any delays our project in Novy Urengoes continues step by step
In Novy Urengoy construction of the Interfield oil and gas pipeline of the Severo-Komsomolskoye field continues. The customer of this construction is the Russian industrial giant SevKomNeftegaz LLC. For a now, the engineers crew of the Beltruboprovodstroy PJSC continues to pull the pipeline siphon across the Pur River.
In accordance with the approved project documentation, our company is laying of gas and oil pipelines in two lines: “Booster compressor station from the Severo-Komsomolsky gas field – to the Gubkinsky gas field and the interfield oil pipeline of the Severo-Komsomolsky field to the River Purpe”.
The main tasks of our company are the laying of oil pipeline line with total length of 73.61 km and a gas pipeline with total length of 67.196 km. In the construction there are several underground crossings will be completed. All crossings of the oil and gas pipeline will be performed by Beltruboprovodstroy PJSC staff by directional drilling method using own equipment and utilities.
Beltruboprovodstroy PJSC is a leader in directional drilling in the CIS industry. Many years of experience, a powerful base of the most modern equipment and highly qualified personnel involved in construction allow us to guarantee for our customers a high degree of reliability of laid pipelines, short terms of work and compliance with all regulatory requirements during the construction of facilities.
Let us remind you that this is not the first international project for our company. Just in recent years, Beltruboprovodstroy PJSC has implemented projects in Bulgaria and Serbia.