At “Gomel – Gorki” main pipeline facility the performing of next closed crossing starts
Glad to share that the construction works on the Beltruboprovodstroy section of the “Gomel – Gorki” main pipeline facility are being carried out according to the schedule.
The construction project held by GomelTransneft Druzhba JSC is already lasting on three months. Till that time at the sections of Beltruboprovodstroy has been completed most part of linear pipeline construction and crossings.
Those days the Beltruboprovodstroy engineering team has approached to the Dobrich River (Gomel Region), where a closed oil pipeline crossing will be performed using the directional drilling technology with a protective case diameter of 800 mm. Pipe diameter is 500 mm. At the moment our drillers have already completed the pilot drilling and take last preparations for the expansion phase.
The successful performance of the work is due not only to the experience of our builders, but also to the especially hot and sunny weather, which, surprisingly, stays in Belarus for the last weeks. Hope it will stay for longer because ahead of our team there are some important stages before the project will be finished.
*the photos are for illustrative purposes only