Return to the work at the Russian Far North
Weather conditions in the Far North allowed BELTRUBOPROVODSTROY JSC to continue works at the facility of “SevKomNeftegas” “Construction of facilities for the Interfield oil and gas pipelines of the Severo-Komsomolskoye field” in the Yamalo-Nenets Autonomous District. Our workers have constructed the main part of linear pipeline and ready to continue performing of the crossings.
After some pause in work caused by snow melting and wetlands of the area, BELTRUBOPROVODSTROY Drilling Team started new stage of construction with the successful implementation of the closed crossing under the communications. The crossing length – 342.5 m, a pipe diameter – 1020 mm. It was performed by directional drilling technology using the world’s most powerful drilling complex Prime Drill PD500.
It have became already the 4-th crossing at that site, performed by our company since the project started in December 2020.
Congratulate the team on a successful start!
*the photos are for illustrative purposes only